The Stratos artificial intelligence datacenter footprint will cover more than 40,000 acres (62 sq miles) over three sites in Box Elder county in north-western Utah. The facility will require about 9GW of power, which is more than the entire state of Utah currently consumes, and suck up a significant amount of water in an area that has been hit by severe drought in recent years.

  • IHeartBadCode@fedia.io
    link
    fedilink
    arrow-up
    1
    ·
    21 days ago

    It’s located on the Ruby Pipeline which will serve as the primary source of energy in the short term. Additionally, the data center being classified as a national security site, is located near the Utah Test and Training Range.

    Longer term the facility is looking at nuclear facilities for power and the possibility for a runway and aviation facilities.

    The primary customer of this facility will be the United States military.